
Melamchi Water Supply Project (MWSP)
was designed to finance four major
components (i) Infrastructure Development,
(ii) Social and Environmental Support;
(iii) institutional reforms; and (iv)
Project implementation Support.
The MWSP was projected to cost US$
464 million in 2000 prices. According
to the original financial plan, ADB
shouldered the largest financing share
(US$120 million equivalent) followed
by the World Bank (US$80 million),
the Japan Bank for International Cooperation
(JBIC), US$52 million equivalent),
NORAD (US$28 million equivalent),
Sida (US$ 25 million equivalent),
the Japan International Cooperation
Agency (JICA, $18 million equivalent),
the Organization of Petroleum Exporting
Countries Fund for International Development
(OFID/OPEC), $14 million equivalent),
and NDF ($9 million equivalent). The
Government's original financing share
in the MWSP was $ 118 million equivalent.
World Bank proposed a PSP financing
plan (Private Sector Participation)
financing plan for institutional reform
components of the project. But this
private lease failed to attract interest
from potential bidders in both tendering
efforts and hence the World Bank decided
to drop proposed funding in June 2002.
Due this, other funding partners has
also lost their interest and hence
delayed the project operation until
new scheme of financing re-designed
and sourced.
After a demonstrated commitment and
initiatives taken by the government,
ADB agreed to recover the financial
lag created and re-structure the project
as Melamchi Valley Subproject (Subproject1)
and Kathmandu Valley Subproject (Subproject2).
Currently, the MWSDB governs only
the Subproject1 activities.
The current financing plan and sources
to respective project task has been
described below:
1.
Government of Nepal
Nepal government has been continuously
putting effort to complete the Melamchi
Water Supply Project and provide safe
drinking water to the people of capital
city, Kathmandu since November 1998
after the establishment of the Melamchi
Water Supply Development Board (MWSDB).
Various researches, studies and
concept has been put forward before
the formal establishment of MWSDB,
it seems that country has already
estimated the future crisis of water
in the capital city and started programming
of Melamchi project since 1990.
Although, Nepal government has allocated
only the 28.56 percent of total estimated
budget to be spent to complete the
Melamchi Water Supply Project, it
has already worked hard to create/collect
the required fund coordinating with
different international/multinational
and bilateral financial institutions.
Keeping the evaluations and follow
up of all sorts of project works,
the government of Nepal has allocated
budget in the following work areas
of the project.
 |
Infrastructure Development
- 36.98 million Out of 148.64
million, i.e. 25 percent of total
cost of this component. |
. |
Social and Environmental Support
- 1.67 million out of 8.31 million
investment in this sector (20
percent of total cost) |
 |
Project Implementation Support
- 14.87 million out of 45.66 million
investment in this sector (33
percent) |
Also, the government of Nepal bears
100 percent expenses on estimated
16.67 million US$ tax and 19 percent
(2.97 million US$) of contingencies
estimated for physical and prices
contingencies our of 16.02 million
US$.
Hence, in total the government of
Nepal bears a sum of 73.16 million
US$ out of 235.31 million US$ estimated
to invest in the project construction
i.e. approximately 31.02 Percent of
cost allocated for Subproject I of
Melamchi Water Supply project.
For detail information regarding
the government of Nepal please visit
– http://www.nepalgov.gov.np/
2.
Asian Development Bank (ADB)
ADB is the major donor for the Melamchi
Water Supply Project. A total of 91.72
million US$ out of estimated 235.31
has been financed as a Loan. This
amount will be approximately 39 percent
of the total cost estimated to complete
the task as assigned to Subproject
1 of Melamchi Water Supply Project.
The sum from the ADB Loan shall be
covered as follows:
 |
Infrastructure Development
– 60.49 million Out of 148.64
million, i.e. 41 percent of total
cost of this component. |
. |
Social and Environmental Support
– 6.64 million out of 8.31 million
investment in this sector (80
percent of total cost of this
component. |
 |
Project Implementation Support
– 15.50 million out of 45.66 million
investment in this sector (34
percent) |
 |
A sum of 9.08 m US$ out of 16.02
m US$ has also been estimated
to finance for physical and price
contingencies from the Loan of
ADB. |
The work under Infrastructure Development
are:
| (i) |
construction of
26.3 km long tunnel |
| (ii) |
building and maintenance of
access roads including – AAR,
UAR and MAR; and |
| (iii) |
construction operation and
maintenance of Camp site offices
Pulbazar and different Adit Access
points. |
For further information regarding
ADB please visit: http://www.adb.org
3.
Japan International Cooperation Agency
(JICA)
The loan agreed to provide by the
Japan Bank for International Cooperation
(JBIC) has now been invested in the
Melamchi Water Supply project through
JICA. A sum of estimated 46.28 million
US$ out of 235.31 million US$ i.e.
20 percent of total cost incurred
in the subproject1 of Melamchi Water
Supply Project.
Basically, out of the total Loan
amount i.e 46.28 million, 37.47 million
US$ will be invested in order to construct
the water treatment plant at main
outlet of the 26.3 Km long tunnel
at Sundarijal. Rest of the loan amount
(8.81 m US$) will be spent on different
training required to operate the water
treatment plant after completion.
Also, this loan will contribute for
physical and price contingencies.
In summary the Fund from JICA/JBIC
will cover:
| (i) |
Construction of
Water Treatment Plant (WTP) at
Sundarijal Mahankal |
| (ii) |
Consulting and management expenses
for Water Treatment Plant
Water Treatment Plant Consultant |
For further information regarding
JICA please visit -
www.jica.go.jp/english/
4.
Organization of Petroleum Exporting
Countries (OPEC)
Organization of Petroleum Exporting
Countries, OPEC Fund for International
Development has also supported an
important part of project task has
provided loan for the construction/building
of access roads amounted to 13.70
million US$. This amount is around
6 percent of total (235.31 million
US$) cost allocated for Melamchi Valley
Sub-project (Subproject 1). This contributed
to almost 50 % of total cost of the
Road component for:
| (i) |
Audit Access Roads |
| (ii) |
Upgrading Access Roads |
For further information regarding
OPEC please visit - www.opec.org
5.
Nordic Development Fund (NDF)
Nordic Development Fund has also contributed
to an integral part of project cost.
The fund from NDF has been spent in
consulting/expert services of Design
and Supervision of 26.3 Km long tunnel.
Total amount i.e. 10.45 million US$
will be 4 % of total cost subproject
1 which occupies around 66 percent
of total Design and Supervision cost
of the project.
For detailed information regarding
NDF please visit -
http://www.ndf.fi/home.shtml
|