| |
Mr.
Som Nath Poudel
Deputy Team Leader
Project Management Consultant
Melamchi Water Supply Project |
Comment
to the Article
"Threat
to Super High Head Langtang Projects" by Dr. A. B. Thapa
Dr. A.B. Thapa published an interesting
and thought provoking technical article in the August 16,
2002 issue of Spotlight magazine entitled "Threat to
Super High Head Langtang Projects" in which he provided
his insight and thoughts on the integrated water resources
planning and development for the Langtang, Melamchi and Kulekhani
rivers. The rivers are the sources for large, complicated
and successive transbasin diversion projects. These projects
criss cross the country from the most Northern point to the
Southern borders of Nepal. His theory lacks consideration
of technical, economical and socio-political realities. Let
us take a realistic look at his theories in comparison to
actual conditions. The Gandak Basin Master Plan Study identified
the hydropower potential of the Langtang river based on the
initial head and assumed discharge data available at different
locations along the river. The proposed high dam at Jaithang
for Langtang-1 would have to be approximately 300 m high to
realize the suggested full supply level of 3,995 meters (amsl).
At this altitude the backwater level would reach the tongue
of Langtang glacier which would cause the reservoir to contain
ice particles most of the year. The back water level would
directly threaten the existence of the glacier and could have
a disastrous impact on the ecology of the World famous Langtang
National Park. The 30 - 40 m thick loose moraine deposit underneath
the dam renders the proposition of a high dam technically
and economically impractical. The river gradient at the dam
location is very steep and the assumed 180 million m3 storage
capacity (compared with 7.4 million live storage of Ghodatabela)
site is not a very realistic figure. The minimum measured
flow of the river, 15 km downstream at Ghodatabela (3,000
m/amsl), is below 4 m3/s and the average annual flow calculated
by the Nepal Electricity Authority (NEA) is approximately
10-12 m3/s. Therefore, the average annual flow at 4,000 m
amsl would be substantially less than the 10 m3/s, instead
of 15m3/s mentioned in the article. Since, between the 3,995
m elevation and the Ghodatabela there are several smaller
tributaries that join the river. Hence, the generation figure
would be much less than the 70 MW mentioned. Concerns on environmental
impacts and consideration of the technical and economical
factors for this site indicate further studies would be wasted
and of no practical use.
The Langtang-2 storage project, dam site located at Ghodatabela
(3,000 m amsl) with a very high (1,570 m gross) head is an
excellent medium sized storage project identified by NEA after
pre-feasibility level studies of several alternatives. Preliminary
design shows there is a cumulative 12 km long 5 drop shafts
cum horizontal pressure tunnels and 93 m high dam with 7.4
million m3 live storage capacity. The project is designed
to have a 218 MW installed capacity. It yields 950 GWh per
annum with 304 GWh dry season energy and specific energy cost
is forecasted to be approximately 3.85 cents/kWh. The tail
water of the Langtang-2 is dropped in the Bhote Koshi river
at an elevation of 1,421 m amsl. (for more information refer
Nepal Electricity Authority, Fiscal year 2001/02 - A Year
In Review.
The issue raised here is that if you
direct the Langtang river flow to Melamchi basin from Ghodatabela,
you would then need to have an approximately a 22 km long
tunnel crossing the National Park from west to east and impinging
on the fragile ecology and geology of the area which could
have unknown impacts. The generation cost per unit for this
alternative would be substantially higher than 4 cents/kWh
compared with the unsupported 2 cents/kWh stated by Dr. Thapa.
The Mini Langtang Project on the tailend of Langtang-2, is
licensed to a Private Developer. It is a 14 MW project with
a 200 meter head. This project, still being considered would
overlap with Langtang-2. With the full development of the
bigger project, this mini project may well be bought back
by the other developer.
The theory offered that with the Langtang Diversion, the Melamchi
Tunnel would be expected to run at full capacity of approximate
15m3/s throughout the year and generate 35 MW power is simply
not true. During the dry season (January - April) the maximum
flow in the tunnel would only be 8 - 10 m3/s and would generate
15 - 20 MW power. If this option is to be considered, then
the suggested power could be generated right in the Melamchi
Valley itself without any need to divert the river flow to
the Kathmandu Valley.
The question of water supply to the Kulekhani river is a difficult
one. The difference in elevation between the Kathmandu Valley
(1,430 - 1,450 m) to the Kulekhani Reservoir with an elevation
of 1,530 m is approximately 100 m higher. In addition to about
15 km surface channel, it would necessitate a pump station
to lift water and a further 13 - 14 km of tunnel for diversion
or extra tunnel caverns are needed to go round the valley
mountains. It would add a further 10 to 15 km to the tunnel
length. Technically, this can be done. The Kulekhani reservoir
is designed to accommodate the full flow of Kulekhani river
water and generate 60 MW of power. If it is necessary to increase
the capacity to generate an extra 300 MW power, dam height
must be increased. Environmentally, technically and economically
these issues require to be seriously studied. A separate parallel
tunnel to divert the additional water and new power house
would be needed. The current Kulekhani Project does not have
the capacity to handle this added burden. The old system would
have to be dismantled and a new system constructed.
Analysis of Dr. Thapa's proposal shows that after traversing
close to 100 km of terrain mostly utilizing underground pressurized
water conduits would produce a gross total head of less than
2,300 m. Ghodatabela, at an elevation of 3,000 m, is the highest
point technically and economically feasible for the diversion
of Langtang water for a detoured journey to the Hetauda at
an elevation of approximately 700-800 m. Recent hydrological
information shows that the annual average diversion discharge
is not more than 10 m3/s (refer recent NEA studies). Assuming
a net head of 2,000 m and an average annual flow through the
turbines of 10 m3/s could produce a maximum of approximate
175 MW base load with a continuous generation capacity of
1,534 GWh of energy. Considering the significant cost for
generation of this energy, the idea of providing cheap or
almost free drinking water to the Kathmandu Valley at the
cost of the electricity is nothing more than a dream. Please
remember that Langtang 2 is already under consideration and
estimated energy yield is 950 GWh.
The another serious issue raised by
Dr. Thapa was "Inhabitants of the Valley, however, are
unaware that they would have to pay a monthly bill of about
Rs. 4,000 at present price levels after the Melamchi Project"
which is not based on the actual facts and is totally incorrect.
If all financing for the Melamchi Project and related components
were to be passed on to the Kathmandu Valley Water Utility
(KVWU) as loans, then the tariff would be approximately NRs.
57/m3 in 2007 (at 2000 prices) to meet operating costs and
debt servicing at an interest rate of 8%. The minimum level
of Project cost repayable by KVWU is likely to be only 50%
with the balance booked as a Grant. In this event the financial
analysis allows for a tariff of Rs. 25 /m3 to meet full debt
service in 2007 (Refer Melamchi Project, Financial Analysis,
Nov. 2000). Therefore, the average tariff level to be set
in the post Melamchi scenario is estimated to be between NRs.
26-28/m3. This allows that for a medium income family consisting
of an average of 5 members would be paying approximately Rs.
560 as a normal monthly tariff for their water consumption.
The theories of Dr. Thapa although interesting are not based
on actual considerations and need to be more properly studied
and supported with more accurate facts and figures than was
presented in the article.
Back
|