|
KATHMANDU
WATER SUPPLY IMPROVEMENT
DONORS CONTRIBUTION CRUCIAL
Authored
By: Madan Shankar Shrestha
Date: August 2, 2002
Click
Here to view the Original Published Version in The Rising
Nepal
Kathmandu had the first taste of piped
water supply more than a century ago. The Bir dhara system
(1895 AD) designed by the British engineers supplied water
from the Shivapuri (Budhanilkantha) watershed area. The TriBhimdhara
system (1930) followed tapping water from Balaju (Alley, Boudhe,
Bhandare) area. The Dudhpokhari system was also designed by
the British engineers. All these system supplied water to
most of the Rana palaces and few public taps, although the
privileged few also enjoyed private taps. With the construction
of Sudarijal water treatment plant under the cooperation of
the Indian Government in 1966, private taps were connected
in the Kathmandu area as demanded by the consumers. In a true
sense first full commercial operation of water supply system
commenced with the completion of the Sundarijal water supply
system.
A master plan to improve and extend
water supply in the Valley was prepared in 1974 with the assistance
of United Nations Development Program. This master plan was
the basis for the first World Bank/IDA funded project in 1975.
The first five production wells and Pharping/Sainbhu water
supply system were constructed under this project. The volume
of water supply in the Patan area almost increased five folds
with the completion of Sainbhu system. Private taps could
be distributed freely in the Patan area. Initially the Sainbhu
system could supply some areas in Kathmandu as well. Large
scale metering of water tap was introduced during the first
IDA project. Meanwhile the German government assisted to improve
water supply in the Bhakatpur area under the Bhaktapur Development
Project.
The World Bank funding in Kathmandu water supply continued
with the implementation of second and third IDA project between
1980 - 1987. More than 30 deep tube wells were constructed
to tap groundwater which were considered to be the low cost
option compared to tapping of remaining surface water sources.
Hotels and industries also started drillin
study of outside valley water sources
was carried out in 1988 to tap water from outside the Valley
sources. 20 options including bringing in water from Melamchi,
Indrawati, Rosi were studied. Although pumping water from
Indrawati was found to be the least cost option (based on
initial investment cost), it was opted out because of the
high operation and maintenance cost involved in high head
pumping of Indrawati water. Melamchi and Rosi scheme competed
fairly among the gravity system. Environmental impact study
funded by UNDP and executed by the World Bank (1989) confirmed
Melamchi to be the better option. Eventually a full scale
feasibility study of Melamchi scheme was carried out in 1991.
Once again this study was funded by UNDP and executed by the
World Bank. While the feasibility study of Melamchi scheme
was being carried out, the Japanese government assisted in
carrying out a master plan study of in Valley sources aimed
at developing the in Valley sources as a short term and medium
term bridging gap until the Melamchi scheme was commissioned.
The construction of Mahankalchaur and Bansbari water treatment
plant funded by the Japanese government grant in line with
the master plan contributed immensely to avert water crisis
in Kathmandu, as the start of the Melamchi project was delayed.
The master plan study concluded that groundwater in the Valley
was being mined lowering of groundwater table at an alarming
rate and pumping of groundwater should be reduced by almost
50% in order to sustain its use. The study also concluded
that tapping additional volume of surface water was feasible
at least in the wet season. Hence the conjunctive use of water
with the use of more surface water for 8 months in an year
and resting of wells, and increased use of groundwater for
rest of the 4 months during the dry season were recommended.
The World Bank had earlier assisted
NWSC in preparing a 15 years (1990 - 2005) comprehensive development
plan (CDP). A full scale designing of Melamchi project in
the first five years of CDP and construction during the following
years were included in the CDP. The targeted date for completion
of Melamchi project was set at year 2000. Before the construction
of Melamchi works, priority rehabilitation and extension works
were planned to be completed. The World Bank assistance in
Kathmandu water supply continued with the funding of Urban
Water Supply and Sanitation Rehabilitation Project (UWSSRP)
in 1992 in line with the CDP. Meanwhile other donors joined
hands with the World Bank, UNDP in institutional improvement,
consumer education and community participation program, and
the Norwegian Government in leakage control. The UWSSRP was
designed to rehabilitate and extend water supply and sewerage
system and to strengthen the institutional capacity of NWSC
in parallel with the physical works. As there was slow progress
in the NWSC institutional improvement, the World Bank at the
time of mid term review of the UWSSRPt (1997) revised the
project component. The UWSSRP closed in 1999 without achieving
much of its objectives. Rehabilitation and extension of distribution
network which was envisaged to be completed before it received
Melamchi water remains incomplete which however is now included
in the Melamchi project.
Meanwhile search for funding of Melamchi
project continued. The UNDP assisted in conducting a bankable
feasibility study ( 1996 ) aimed at studying the possibility
of commercial banks investing in the Melamchi project HMG
established Melamchi Water Limited in 1997 to implement Melamchi
project through internal and/or external funding.. As the
Asian Development Bank, the Norwegian Government and some
other donors took interest in funding the Melamchi project
the HMG established the Melamchi Water Supply Development
Board in 1998. At present ADB, the Japanese Government, the
Japanse Bank for International Cooperation (JBIC), the Norwegian
Government, the Swedish Government, OPEC Fund and the Nordic
Development Fund (NDF) are involved in the Melamchi project.
The Japanese government is continuing its assistance to implement
the Manohara scheme and improving the Sundarijal system in
order to supplement Kathmandu water supply prior to the completion
of the Melamchi project.
More than 25 long years of involvement
of the World Bank in Kathmandu water supply concluded recently.
Despite sincere efforts by HMG and the continued support from
the World Bank, the water supply situation in Kathmandu is
still far from satisfactory, non the less, the supply volume,
service area and population served has grossly increased from
what it was in 1975 to what it is today. The situation would
have worsened without the World Bank and other donors assistance.
Back
|